The Dholera airport is being built at Navagam village in Ahmedabad district, about 20 km from the core of Dholera SIR and close to the Ahmedabad–Dholera Expressway. On 14 July 2026, Civil Aviation Minister K. Ram Mohan Naidu said overall work was 80% complete. The runway, taxiway and ATC buildings were finished, and the passenger terminal was 75% done. He said the airport would be operational within three months. DGCA licensing was in progress as of July 2026. The official opening date and first flight are tracked in the live updates below.
Live Updates: Dholera Airport Status Log (Newest First)

18 October 2026: Page refreshed. This page now replaces our six older airport articles. We will add the DGCA licence, opening date and first flight here as soon as they are officially announced.
September 2026: Site work deadline. The Ministry of Civil Aviation had directed that all site work be completed by September 2026.
14 July 2026: Minister’s progress review. According to News On AIR, Union Civil Aviation Minister K. Ram Mohan Naidu said overall work stood at 80%. The runway, taxiway and air traffic control (ATC) buildings were 100% complete, and the passenger terminal was 75% complete. He said the airport would become operational within three months, and that MRO hangars are planned for C-295 aircraft. DGCA licensing was in progress at the time.
June 2026: Trial landing. A trial aircraft landing at the site was reported.
January–February 2026: Calibration flights. Calibration flights were carried out at the site, an essential step before an airport can handle regular traffic.
14 June 2022: Cabinet approval. The Cabinet Committee on Economic Affairs (CCEA) approved the project, with Phase 1 estimated at about ₹1,305 crore.
2012: Developer formed. DIACL was set up as the special purpose vehicle (SPV) to build and run the airport.
Dholera Airport at a Glance
| Item | Details |
| Official name | Dholera International Airport |
| Location | Navagam village, Ahmedabad district, Gujarat |
| Distance from Dholera SIR core | About 20 km |
| Nearest major road | Ahmedabad–Dholera Expressway |
| Developer | Dholera International Airport Company Ltd (DIACL), set up in 2012 |
| Shareholding | Airports Authority of India (AAI) 51%, Government of Gujarat 33%, NICDIT 16% |
| Approval | CCEA, 14 June 2022 |
| Cost | Phase 1: about ₹1,305 crore; all three phases: about ₹1,712 crore |
| Runway | Reported as 3,200 m in Phase 1, 4,000 m in later phases |
| Progress (July 2026) | 80% overall; runway, taxiway, ATC 100%; terminal 75% |
| Opening date / first flight | To be announced |
| Projected traffic (2026) | 3 lakh passengers, 20,000 tonnes of cargo |
| Projected traffic (20 years) | 23 lakh passengers, 2.33 lakh tonnes of cargo |
The traffic figures are the government’s 2022 projections, not actual numbers. We will replace them with real traffic data once flights begin.
Dholera Airport Location and How to Reach It

The Dholera airport location is Navagam village in Ahmedabad district, Gujarat. The site is about 20 km from the core of the special investment region and sits near the Ahmedabad Dholera Expressway, the main road link between Ahmedabad city and Dholera.
For investors, this location matters because the airfield is close to both the SIR core and the expressway. The road, the airport and the industrial zones are meant to work together as one corridor, which is what gives land in this belt its long-term story.
By road
The expressway from Ahmedabad is the main approach. A dedicated Dholera airport road is expected to connect the terminal with the expressway and the SIR’s internal road network.
By rail
A rail link is part of the wider connectivity plan for the region. Our coverage of the Dholera railway station project explains the approved route and its current progress.
By metro
There are proposals to extend Ahmedabad’s metro toward the airport. Our post on the Ahmedabad Metro Phase 3 route explains what has been proposed and what is still at planning stage.
Practical tip: until official travel times are published, keep buffer time when you plan a site visit, and check road and traffic conditions before you leave.
Current Status: Runway, ATC, Terminal and Licensing

Here is where each part of the project stood at the last official update on 14 July 2026, along with what was still pending.
Runway and taxiway: complete. The minister confirmed both were 100% finished. Runway length is reported as 3,200 m in Phase 1, extending to 4,000 m in later phases. Runway length decides which aircraft can operate.
ATC building: complete. The air traffic control buildings were also 100% finished. Calibration flights were carried out in January–February 2026, and a trial aircraft landing was reported in June 2026.
Passenger terminal: 75%. The terminal was the main open item in July. Interiors, baggage systems and passenger facilities usually take the last few months of any airport project, so this is the part to watch.
Licensing: in progress. An airport in India needs an aerodrome licence from the Directorate General of Civil Aviation (DGCA) before commercial flights can begin. In July 2026, DGCA licensing was in progress.
Opening: not yet confirmed. The minister’s three-month window from 14 July points to around mid-October 2026. Until an airline publishes a schedule, treat any Dholera airport opening date you see online as unconfirmed.
Dholera Airport Project Timeline
| Date | Milestone |
| 2012 | DIACL set up as the SPV (AAI 51%, Gujarat 33%, NICDIT 16%) |
| 14 June 2022 | CCEA approves the project; Phase 1 cost about ₹1,305 crore |
| January–February 2026 | Calibration flights |
| June 2026 | Trial aircraft landing reported |
| 14 July 2026 | 80% overall; runway, taxiway, ATC complete; terminal 75%; DGCA licensing in progress |
| September 2026 | Ministry’s deadline for completing site work |
| October 2026 | Operations expected, per the minister’s July statement |
| Later phases | Expansion across three phases (about ₹1,712 crore in total) |
| About 20 years from 2022 | Projected 23 lakh passengers and 2.33 lakh tonnes of cargo a year |
Dholera Airport City: Cargo, MRO and Aviation Manufacturing

The Dholera smart city airport is planned as more than a passenger terminal. The bigger idea is an airport city: a commercial and industrial zone around the airfield where cargo handling, aircraft maintenance and aviation-linked businesses can cluster. For the region, this is where most of the long-term jobs, and most of the land demand, are likely to come from.
Cargo
The government’s 2022 projection put cargo at 20,000 tonnes in 2026, rising to 2.33 lakh tonnes a year over 20 years. That growth is the important part. Air freight matters most for high-value, time-sensitive goods such as electronics and precision components. Industries like the Tata semiconductor plant are exactly the kind of tenants that rely on fast, secure air cargo, which is why the airport and the SIR’s industrial plans are closely linked.
MRO (maintenance, repair and overhaul)
In July 2026, the minister said MRO hangars are planned for C-295 aircraft. MRO facilities bring skilled, long-term technical jobs and supporting suppliers.
Aviation manufacturing
Aviation manufacturing is part of the airport city vision. We will add company names here only once they are officially confirmed. Until land is allotted and construction starts, treat any “aviation hub” claim as a plan rather than a fact.
What the Dholera Airport Means for Plot Buyers
An operating airport is one of the strongest signals a new city can send. But it is one factor among several, and it does not make every plot nearby a good buy. Here is a balanced view.
Potential benefits
- Connectivity: air access, combined with the expressway, cuts travel time for businesses, employees and visitors.
- Jobs and housing demand: terminal staff, ATC, cargo handlers and MRO technicians all need homes, schools and shops nearby.
- A stronger case for industry: companies choosing between locations look closely at air links, especially for exports.
- Visibility: an operating airport brings Dholera onto the radar of buyers who have never visited.
Risks to weigh
- Opening timelines can slip. The opening date is not confirmed as of this update. Don’t pay a premium on the assumption that flights start on a specific date.
- Projections are not traffic. 3 lakh passengers a year is a modest start. The large numbers are a 20-year projection, and real demand will build gradually.
- Prices may already reflect the news. Compare asking prices with similar land a few kilometres further out before you commit.
- Restrictions near airports. Land close to an airfield can face height limits and noise-related land-use rules. Check the plot’s zoning in the Dholera SIR development plan and any height clearance requirements.
- Paperwork matters more than distance. Confirm clear title, non-agricultural (NA) status, the town planning scheme, and RERA registration where applicable.
- Time horizon. Land in a new city is a long-term holding. Buy only money you won’t need back in the short term.
Our view: if you have a five to ten year horizon and you verify the paperwork, a well-located plot with clear title can benefit from the airport city’s growth. If you need quick returns, the risks above deserve more weight than the headlines.
Our Projects Near the Dholera Airport
Angel Aerocity is our project closest to the airport. It is planned for buyers who want to be positioned for the airport city’s growth while holding a plot with verified documents.
To compare locations and budgets, browse all our plots near Dholera airport, with title documents available for every listing.
FAQs About Dholera International Airport
At the last official update on 14 July 2026, overall work was 80% complete. The runway, taxiway and ATC buildings were finished, the passenger terminal was 75% complete, and DGCA licensing was in progress.
In July 2026 the minister said it would be operational within three months, which points to around October 2026. We will update this answer as soon as the official opening date and first flight are announced.
It is at Navagam village in Ahmedabad district, Gujarat, about 20 km from the Dholera SIR core and near the Ahmedabad–Dholera Expressway.
The site is reached via the Ahmedabad–Dholera Expressway, the main road link from Ahmedabad city. We will add the official distance and travel time once published.
DIACL, a special purpose vehicle set up in 2012. Its shareholders are the Airports Authority of India (51%), the Government of Gujarat (33%) and NICDIT (16%).